don robert wrote:
DOTr completes weight-testing of Dalian trains
By Aerol John Pateña April 20, 2018, 12:06 pm


MANILA -- The Department of Transportation (DOTr) has completed its weighing test of Dalian trains for the Metro Rail Transit Line 3 (MRT-3) railway system Thursday night.

The weight testing conducted at the MRT depot was preceded by a series of procedures, including equipment installation, calibration, weighing of empty trains, and loading of weights. It was witnessed by representatives from TUV Rheinland, members of MRT-3’s Joint ADB-Australia Aid Advisory Panel and the DOTr-MRT 3 management.

The test was done by weighing a Dalian car loaded with 1,464 sandbags each weighing 17.5 kilograms (kg) to simulate the train’s crush capacity of 8 persons per square meter or a total of 394 passengers per car.

"Iyong weight-testing ngayon is part of a broader auditing and acceptance process. Different factors kasi 'yung pumapasok sa tanong na kung acceptable ba siya or hindi. Our independent auditor, na nagsimula noong January, will put all their findings together once all of the processes are done. They will give their assessments and recommendations. (The weight testing is part of a broader auditing and acceptance process. There are different factors that need to be determined if the trains will be acceptable or not. Our independent auditor, which started last January, will put all their findings together once all of the processes are done. They will give their assessments and recommendations),” DOTr Undersecretary for Railways Timothy John Batan said in a press briefing Thursday after the tests at the depot.

The MRT-3 management expects TUV Rheinland to submit its comprehensive audit report on the Dalian trains within one to two weeks.

TUV Rheinland recommended the weight-testing in Manila after the previous project team that handled the procurement and delivery of the cars failed to attend and witness the weight-testing done in Dalian, China in 2015.

http://www.pna.gov.ph/articles/1032639

_________________
God(x) + Science(y) = Faith(x + y)


Top
 Profile  
 
PostPosted: Fri May 25, 2018 3:30 pm 
Offline
Heavyweight
User avatar

Joined: Thu Jan 19, 2006 3:47 pm
Posts: 24559
pubriiiiiing, ano ang bago mong pakulo ngayon na napulot sa mga ka dede es mo? nasupla na yung "election kasi nung 2016" fake news, dapat me back up plan ka.

para mapanindigan mo yung mali mong paniniwala. tutal na basa ka na rin lang, maligo ka na. :lol:

_________________
"I will make you an offer you can't refuse." - Michael Corleone


Top
 Profile  
 
PostPosted: Fri May 25, 2018 3:46 pm 
Offline
Heavyweight
User avatar

Joined: Sat May 24, 2008 10:23 pm
Posts: 4814
don robert wrote:
pubriiiiiing, ano ang bago mong pakulo ngayon na napulot sa mga ka dede es mo? nasupla na yung "election kasi nung 2016" fake news, dapat me back up plan ka.

para mapanindigan mo yung mali mong paniniwala. tutal na basa ka na rin lang, maligo ka na. :lol:



anong supla????

:lol: :lol: :lol:

balikan mo un time line mo... at ayusin mo...

ilagay mo lahat nung nangyari, bago at kung bakit Dalian ang napili.

hindi ka naman Lady Justice na nakapiring kaya bulag sa katotohanan...

wag mong ipahid ung paniniwala mo sa ibang tao, para masabi mo sa sarili mo na tanga ka este tama!

_________________
God(x) + Science(y) = Faith(x + y)


Top
 Profile  
 
PostPosted: Fri May 25, 2018 3:54 pm 
Offline
Heavyweight
User avatar

Joined: Sat May 24, 2008 10:23 pm
Posts: 4814
don robert wrote:
pubriiiiiing, ano ang bago mong pakulo ngayon na napulot sa mga ka dede es mo? nasupla na yung "election kasi nung 2016" fake news, dapat me back up plan ka.

para mapanindigan mo yung mali mong paniniwala. tutal na basa ka na rin lang, maligo ka na. :lol:


don robert wrote:
Pubring, bigyan kita ng short timeline summary:
June 2013, na qualify ang Dalian
Nov 2013, nag post qual ang DOTC sa Dalian
Jan 2014, inaward ng DOTC ang contract sa Dalian
Feb. 2014, pumunta ng korte ang MRTC (owner ng MRT) for TRO, which was granted. but before end of February 2014, na cancel ang TRO. nag appeal ang MRTC
May 2015, naglabas ng decision ang Court of Appeals, upholding the decision of the lower court in dismissing the TRO it issued. nag appeal ulit ang MRTC. But the government went ahead with the deal sa Dalian
Aug 2015, dumating prototype from China
Jan 2016, simula nang dumating ang mga trains
April 2016, nag start nang mag test run ang mga trains


:lol: :lol: :lol:

sabi mo nga kay mang mullatz dati...
provide links or that's hearsay!

:lol: :lol: :lol:

Quote:

Explain MRT scandal, Mar told
July 01, 2015
http://manilastandard.net/news/-main-stories/181267/explain-mrt-scandal-mar-told.html

FORMER Negros Oriental congressman Jacinto “Jing” Paras challenged DILG secretary Mar Roxas on Tuesday to reveal what really happened in the MRT bribery scandal since Roxas was the one who initially signed the billion peso MRT maintenance contract in favor of PH Trams.
....


_________________
God(x) + Science(y) = Faith(x + y)


Top
 Profile  
 
PostPosted: Fri May 25, 2018 7:43 pm 
Offline
Heavyweight
User avatar

Joined: Thu Jan 19, 2006 3:47 pm
Posts: 24559
pubriiiing, please come back where you belong! :lol:

gumagawa ka na naman ng kwento.

meron ka na namang "ilagay lahat". :lol:
kayo talaga, kuhang kuha nyo yung style ng mga republican fanatics.

you want me to prove something that you don't name, basta... lahat? :lol:

sa kabila issue mo sa MRT na sinadyang i-delay delivery kasi eleksyun (WITHOUT PROOF). tapos nung na supla ka duon, eto ka na naman at panibagong narrative naman, kesyo ba't Dalian ang pinili. anyare sa "eleksyun kasi" angle? :lol:

at links? basahin mo ang link na binigay ko sa disisyun ng CA. hindi ka kasi nagbabasa, kaya ka nasusupla.

pubriiiiiing, please comeback where you belong! :lol:

_________________
"I will make you an offer you can't refuse." - Michael Corleone


Top
 Profile  
 
PostPosted: Sat May 26, 2018 12:15 am 
Offline
Heavyweight
User avatar

Joined: Sat May 24, 2008 10:23 pm
Posts: 4814
don robert wrote:
pubriiiing, please come back where you belong! :lol:

gumagawa ka na naman ng kwento.

meron ka na namang "ilagay lahat". :lol:
kayo talaga, kuhang kuha nyo yung style ng mga republican fanatics.

you want me to prove something that you don't name, basta... lahat? :lol:

sa kabila issue mo sa MRT na sinadyang i-delay delivery kasi eleksyun (WITHOUT PROOF). tapos nung na supla ka duon, eto ka na naman at panibagong narrative naman, kesyo ba't Dalian ang pinili. anyare sa "eleksyun kasi" angle? :lol:

at links? basahin mo ang link na binigay ko sa disisyun ng CA. hindi ka kasi nagbabasa, kaya ka nasusupla.

pubriiiiiing, please comeback where you belong! :lol:


:lol: :lol: :lol:

kahit ano na lng, basta may masabi lng tlaga ano?

mahirap bang hanapin ung mga article patungkol sa TIMELINE na sinabi mo...

eto oh sama mo sa time line mo...

Quote:
Japanese, German techs detail Dalian train defects
Read more at https://www.philstar.com/opinion/2018/05/25/1818344/japanese-german-techs-detail-dalian-train-defects#tvUGla55a76M5W6t.99
...
TUV Rheinland technicians saw similar design and manufacturing faults. Deviating from contract specs, Dalian lacked requisite safety and performance certifications. DOTr hired the German quality-audit firm in Feb.

...


ang tanging pagkakaiba mo na lng kay Adme ay republican sya... un lng...

pro ung estilo mo sa pagrebutt at comprehension, parehong pareho... kumbaga at the same mold...

:lol: :lol: :lol:

wag mo kaming idamay sa pagkakamali mo... kung binoto mo si Aquino at nagvigil ka pra manalo si Roxas, wag mo kaming damay dyan...

mali mo yan, maging lalaki ka nman paminsan-minsan... ke-simple simple lng nyan di mo pa magawa...

_________________
God(x) + Science(y) = Faith(x + y)


Top
 Profile  
 
PostPosted: Sat May 26, 2018 12:38 am 
Offline
Heavyweight
User avatar

Joined: Thu Dec 02, 2004 2:10 pm
Posts: 17994
Location: Cbo.LP.HK
Naku! Paano yan? :shock:

_________________
"Here’s to a long life and a merry one, A quick death and an easy one, A pretty girl and a true one, A cold beer and another one." - Lewis Henry


Top
 Profile  
 
PostPosted: Sat May 26, 2018 1:12 am 
Offline
Heavyweight
User avatar

Joined: Thu Jan 19, 2006 3:47 pm
Posts: 24559
pubringjuandelacruz wrote:
don robert wrote:
pubriiiing, please come back where you belong! :lol:

gumagawa ka na naman ng kwento.

meron ka na namang "ilagay lahat". :lol:
kayo talaga, kuhang kuha nyo yung style ng mga republican fanatics.

you want me to prove something that you don't name, basta... lahat? :lol:

sa kabila issue mo sa MRT na sinadyang i-delay delivery kasi eleksyun (WITHOUT PROOF). tapos nung na supla ka duon, eto ka na naman at panibagong narrative naman, kesyo ba't Dalian ang pinili. anyare sa "eleksyun kasi" angle? :lol:

at links? basahin mo ang link na binigay ko sa disisyun ng CA. hindi ka kasi nagbabasa, kaya ka nasusupla.

pubriiiiiing, please comeback where you belong! :lol:


:lol: :lol: :lol:

kahit ano na lng, basta may masabi lng tlaga ano?

mahirap bang hanapin ung mga article patungkol sa TIMELINE na sinabi mo...

eto oh sama mo sa time line mo...

Quote:
Japanese, German techs detail Dalian train defects
Read more at https://www.philstar.com/opinion/2018/05/25/1818344/japanese-german-techs-detail-dalian-train-defects#tvUGla55a76M5W6t.99
...
TUV Rheinland technicians saw similar design and manufacturing faults. Deviating from contract specs, Dalian lacked requisite safety and performance certifications. DOTr hired the German quality-audit firm in Feb.

...


ang tanging pagkakaiba mo na lng kay Adme ay republican sya... un lng...

pro ung estilo mo sa pagrebutt at comprehension, parehong pareho... kumbaga at the same mold...

:lol: :lol: :lol:

wag mo kaming idamay sa pagkakamali mo... kung binoto mo si Aquino at nagvigil ka pra manalo si Roxas, wag mo kaming damay dyan...

mali mo yan, maging lalaki ka nman paminsan-minsan... ke-simple simple lng nyan di mo pa magawa...



pubriiiiiiing! binabasa mo ba yung article na pino post mo?

Image

natawa ako ng husto napa utotl ako! :lol:

ito yung pinakapaburito kong part ng article mo ni Jarius Bondoc:

Quote:
But higher-ups are indecisive, DOTr insiders say in sharing the audits.
Read more at https://www.philstar.com/opinion/2018/0 ... UTh0YtZ.99


kaya walang official quote kasi wala namang nilabas pa. kesyo... indecisive daw. :lol:

on a serious note, yung audit results din inaantay ko. sabi nung February this year, sa March daw. nung dumating ang March, sa April naman daw ilalabas. nung dumating April, sa May naman. next week, June na. di ka ba nagtataka ba't antagal mailabas? can you smell, what the rock is cooking? :lol:



at dun sa timeline, kung makabigay ako ng links sa lahat na timelines ko dun, mag self ban ka for one month?

katulad ni Duterte na nangakong mag jetski sa spratly... takot mo lang.

:lol:

_________________
"I will make you an offer you can't refuse." - Michael Corleone


Top
 Profile  
 
PostPosted: Sun May 27, 2018 1:34 pm 
Offline
Heavyweight
User avatar

Joined: Sun Oct 08, 2006 8:18 am
Posts: 27974
Location: JARO,Iloilo
Japanese, German techs detail Dalian train defects


GOTCHA - Jarius Bondoc (The Philippine Star) - May 25, 2018 - 12:00am
Return those trains to China to fix the many defects. That’s the recommendation of Japanese evaluators of the 48 MRT-3 railcars from Dalian Locomotive & Rolling Stock Co. German engineers separately noted the same faults, and told the Dept. of Transportation to act accordingly. Ride safety, reliability, and comfort depend on it.

Dozens of flaws have been found. Among those are uninspected, untested basic components and safety features. Examples: wheels, axles, brakes, auto-doors, vibrations, interior noise, lighting, ventilation and air conditioning, flooring, roof, driver’s cab, and electrical couplings.

Those are on top of earlier bared serious design flops. The railcars, or coaches, are 3.3 tons overweight and the chassis ill fit. Configured for four-coach train sets, each train would be 13.2 tons heavier. Wrong sized, they cannot be hoisted for inspection and repair on existing hi-precision equipment at the MRT-3 depot.

“The cars should be returned to Dalian factory and rebuilt,” experts from Japanese giant Sumitomo Corp. concluded in Apr. Rework should be “from design qualification until factory acceptance under supervision of a rail consultant and/or DOTr with full responsibility” – meaning, begin again. In Mar. the Japan International Cooperation Agency, from which DOTr is borrowing to rehabilitate MRT-3, called in Sumitomo as the commuter railway’s original constructor and maintenance servicer.

Sumitomo stated: “As a result of the assessment of the Dalian reports, it can be concluded that, in fact, all 48 cars did not have any kind of certifications, which should have been used as evidence to verify achievement of all performance tests required for train system, such as design qualification, proper procurement, correctness of manufacturing, operating performance, insurance of safety, etc. This means that the Dalian cars are not reliable, they cannot be considered as qualified cars and nobody can ascertain that the(y) are safe passenger railcars.”

Dalian had not checked the 48 coaches for most of the dozens of engineering specifications. The few tests done in-factory were only on one to three units, Nos. 3102, 3103, and 3104. Lesser inspections after delivery in Manila did not identify the coach number, thus pointless.

TUV Rheinland technicians saw similar design and manufacturing faults. Deviating from contract specs, Dalian lacked requisite safety and performance certifications. DOTr hired the German quality-audit firm in Feb.
DOTr should have acted at once on Sumitomo and TUV Rheinland’s findings. Transport Sec. Arthur Tugade and Railways U-Sec. Timothy John Batan repeatedly said before that they would abide by the specialists’ assessment of Dalian wares. Singapore, Hong Kong, and Pakistan had returned for retrofitting botched Chinese trains.

But higher-ups are indecisive, DOTr insiders say in sharing the audits. Dalian and Chinese officials reportedly are pressuring them to pay up. Yet nobody at DOTr wants to sign any payment processing.

Past transport officials indented in 2013 the P3.8-billion fabrication of 48 coaches. Fifteen percent, P565 million, was advanced. Dalian was unqualified, insiders allege, because adept only in heavy-rail cars pushed or pulled by locomotives, not motorized light-rail vehicles. MRT-3 ex-general manager Al Vitangcol exposed in 2015 a five-percent kickback, P190-million, from Dalian’s local brokers to the contract handlers.

Railcars are not bought from showrooms like sedans. They are made to fit buyers’ specs. In MRT-3’s case the terms of reference consisted of 600-plus pages. Part of it is that the Dalian coaches must copy the 73 originals from the Czech maker. They must hew in with the tracks, power supply, signaling, stations, depot, repair yard, and existing operation and maintenance equipment.

Some of the other discovered defects and non-inspections are: vehicle body structure, bogey frames, pushing and towing, parking brakes, door frames and controls, auxiliary power switches, battery packs, circuit breakers, gearboxes, power collectors and converters, traction motors, window glasses, wheel articulation, starts and stops, and propulsion.

None of the coaches was test-run for 5,000 kilometers, as required, at varied speeds, curves, slopes, loads, weather, and emergencies. In a mishap, what could happen to a full load of 394 passengers?

Overweight will stress the 48 railcars’ wheels, axles, and tracks, and consequently the 73 older units. Rides would be risky, rickety. With faster metal wear, parts will need frequent costly replacement and repair.


The ill-fit chassis prevents roll-up of the railcars on the giant pit jack. Under-chassis inspection, maintenance, repair, and parts change of wheels, articulators, and brakes, among others, cannot be done. Dalian purportedly wants the machine cut by 25 millimeters to suit the 48 cars. But that would ruin the sensors and stability of the hundred-million-peso equipment that services the 73 other units. Besides, doing that could lead to charges before the Ombudsman for allowing contract breaches.

If up to par Dalian’s units would upgrade MRT-3 to four-car trains from the present three. The power supply and depot already are being modified for that, at hundreds of millions of pesos. Trains would take in more commuters on faster, more frequent rides. Traffic would ease not only along EDSA that MRT-3 traverses, but the whole Mega Manila.

But past transport men fouled up and present ones are in a tizzy. Delivered late and faulty, the Dalian trains have been inoperative since 2016.


Read more at https://www.philstar.com/opinion/2018/0 ... vI0PKUw.99

as i said so, Sa overweight lang hinde talaga pwede..sa mga old riles ..it would cost more ...Bobong engineer mga dilawan


Hayan klaro mga uto-utong dilawan and defecto nang TRAIN :lol:


Ang baba talaga ang quality control nang mga Dilawan Engineer ...kahit certification na tested na ang train e wala.

I work in dubai base on my experience ang lahat nang mag requirement certification testing ay strict and certified bago ma aprove ang contract .
anong classing mga consultant at engineer mayroon tayo dito, THIS IS A CLEAR CORRUPTION :shock: :shock: :shock:



Parang Dengvaxia rin minadali :shock:

_________________
Do not overrate what you have received, nor envy others He who envies others does not achieve peace. - Buddha


Top
 Profile  
 
PostPosted: Sun May 27, 2018 1:47 pm 
Offline
Heavyweight
User avatar

Joined: Sun Oct 08, 2006 8:18 am
Posts: 27974
Location: JARO,Iloilo
none wrote:
Pag luma na ang mga riles dapat conservative na design ang masususnod. hinde na kaya ang allowable load limit, 3 tons marami rami din ang pasahero ang masasakay dyan. tama lang na hinde ginamit ang mga Train na binili ni PNOY. tiyak marami ang madidisgrasya at hinde na tuluyan mag operate ang MRT .



Old riles could not stand and overweight train in a long run and it would cost more replacing the old one ..isa lang yan na nakikita noon marami pa pala over a dozen problem na hinde nakita nang mga bobong engineer na dilawan ....kitam :lol:

_________________
Do not overrate what you have received, nor envy others He who envies others does not achieve peace. - Buddha


Top
 Profile  
 
PostPosted: Sun May 27, 2018 2:17 pm 
Offline
Heavyweight
User avatar

Joined: Thu Apr 25, 2013 4:36 pm
Posts: 7185
Nasaan na si indyinir don robert? Pakisagot naman si indyinir dan. :lol: :lol: :lol:

_________________
"Huwag ninyo galawin ang mga maliit na tao, kasi sila ang nangangailangan ng gobyerno."


Top
 Profile  
 
PostPosted: Sun May 27, 2018 2:20 pm 
Offline
Heavyweight
User avatar

Joined: Thu Apr 25, 2013 4:36 pm
Posts: 7185
Kung si Mar ang nanalo, gagamitin yang mga bagon na yan at kapag may trahedyang nangyari sasabihin na naman ni Pnoy na wala siyang alam. Kailangan talaga ang mga bagon kasi crisis proportion na ang traffic sa edsa at walang nagsabi sa kanya na may diperensya yung mga bagon galing sa Dalian. Parang dengvaxia lang naman.
:lol: :lol: :lol:

_________________
"Huwag ninyo galawin ang mga maliit na tao, kasi sila ang nangangailangan ng gobyerno."


Top
 Profile  
 
PostPosted: Sun May 27, 2018 3:14 pm 
Offline
Heavyweight
User avatar

Joined: Sun Oct 08, 2006 8:18 am
Posts: 27974
Location: JARO,Iloilo
Parang habal habal.lang na nilagyan nang side car. At kinargahan nang apat na tao na ang design is for one person to last for five years according to japanese design..pero hinde pa inabot nang isang taon na overhaul na at maraming nang pinalitan...utak dilawan talaga..no wonder marcos infrastructure oulast the new one under Cory up to present. ..corruption is define by this..sino ang kurakot????

_________________
Do not overrate what you have received, nor envy others He who envies others does not achieve peace. - Buddha


Top
 Profile  
 
PostPosted: Sun May 27, 2018 8:00 pm 
Offline
Heavyweight
User avatar

Joined: Thu Jan 19, 2006 3:47 pm
Posts: 24559
Amiga Dan, hindi official report iyang sinasabi ni Bondoc. wala pang na rerelease na report. na supla ko na yan, kasi pinost din iyan ni pubriiiiiiiing.

ayun, nanahimik tuloy... :lol:

dapat nung March pa ni release ang report, tapos sabi sa April, tapos sabi sa May na, ngayong bwan. eh next week, June na.

ewan ko ba't di pa ni re-release, mukhang me niluluto pa. :lol:

_________________
"I will make you an offer you can't refuse." - Michael Corleone


Top
 Profile  
 
PostPosted: Sun May 27, 2018 8:29 pm 
Offline
Heavyweight
User avatar

Joined: Thu Jan 19, 2006 3:47 pm
Posts: 24559
Quote:
Why is P17-B MRT rehab double Sumitomo’s offer?
GOTCHA - Jarius Bondoc (The Philippine Star) - May 23, 2018 - 12:00am

Image

Transport Sec. Arthur Tugade must explain. Why is he borrowing P17 billion from Japan to rehabilitate the MRT-3 commuter railway? That’s despite Japanese giant Sumitomo Corp.’s offer of only P7.5 billion – nearly P10 billion less – to do the work.

Filipinos are entitled to an answer. Their taxes will pay for the 25-year loan. Far too long has MRT-3 been a milking cow of crooked train officials. For five years till last Nov. it sloppily was maintained at multibillion-peso overprices.

Tugade’s Dept. of Transportation (DOTr) announced last week the forthcoming P17-billion loan. The amount supposedly was arrived at after weeklong technical talks with Japan International Cooperation Agency (JICA).

The scope of work was mentioned in the DOTr press release. But there was no breakdown of the P17 billion beside each work item. It only stated that “the project will cost Japanese yen 34.48 billion, or P16.985 billion.”

DOTr and JICA earlier indicated preference for Sumitomo to handle the rehab. Sumitomo, through MRT-3’s private owner-builder Metro Rail Transit Corp. (MRTC), has quoted only P7.5 billion for the long-overdue work. That offer was sent to Malacañang in 2016, and to Tugade in 2016 and 2017. Sumitomo and MRTC have not received any reply.

Last week’s DOTr press release stated the following rehab works, with no corresponding amounts to justify the P17-billion total: trains, power supply system, overhead catenary system, radio system, CCTV system, PABX public address system, signaling system, rail tracks, road rail vehicles, depot equipment, elevators and escalators, and other station building equipment.

“Rehabilitation and Maintenance project will take 43 months: 31 months for the simultaneous rehabilitation and maintenance works to restore MRT-3 to its original design condition and capacity, and 12 months for the defect liability period,” the DOTr said.

Sumitomo is well versed with the state of MRT-3. With Mitsubishi Heavy Industries it constructed the railway in 1998-1999, then handled maintenance in 2000-2012.

Read more at https://www.philstar.com/opinion/2018/0 ... IkoEAzO.99



natuto na ang gobyerno kaya ayaw na maniwala sa quote ng Sumitomo, na preferred by MRTC. binabarat ang MRT kaya maraming sira.

attack dog ata ng MRTC/Sumitomo itong si Bondoc, daming inside-info kuno na nakukuha, pero halatang self serving sa MRTC at hindi sa gobyerno...

_________________
"I will make you an offer you can't refuse." - Michael Corleone


Top
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 245 posts ]  Go to page Previous  1 ... 10, 11, 12, 13, 14, 15, 16, 17  Next

All times are UTC + 8 hours


Who is online

Users browsing this forum: Google [Bot] and 7 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  

philboxing.com | pinoygreats.com
Powered by phpBB® Forum Software © phpBB Group